As part of the implementation of the "Program of Measures to Increase Raw Hydrocarbon Production in 2017-2021", ERIELL Group, jointly with Uzbekneftegaz JSC, put into commercial operation new wells and gas line reservoirs in the Kashkadarya and Bukhara regions, as well as in the Republic of Karakalpakstan.
In particular, in Karakalpakstan, the directional well No. 69 of the Sharkiy Berdakh field of the Ustyurt Oil and Gas Production Directorate (OGPD) was put into operation. The construction of a gas pipeline with a diameter of 114x6 mm and a total length of 600 m was completed.
The gas line reservoir from GSP-5 Shimoliy Berdakh to the point of connection to the gas pipeline GSP CGTU Arslan of "Sharkiy Berdakh" with a length of 6.2 km is connected to the gas pipeline system and ready for operation. The 8.2 km gas line reservoir from GSP "Kuyi Surgil" and "Arslan" to the Gathering Station of CGTU Arslan is also ready for operation.
In the Bukhara region, well No. 55 of Kulbeshkak field of CGTU Gazliyskiy was put into operation. The flow rate of the well is 157,556 thousand cubic meters per day.
A gas flow line with a diameter of 108x8 mm and a total length of 975 m was laid. In addition, well No. 8 of the Garbiy Khakkul field of CGTU Gazliyskiy was connected to cathode protection.
In the Kashkadarya region, wells No. 317 of the Zevardy field and No. 235 of the Urtabulak field of the CGTU Mubarek were put into operation. A gas flow line with a diameter of 168x6 mm and a total length of 818 m was laid.
Wells N. 22 of Karatepa field, No. 70E of the Topichaksoy field of CGTU Shurtan and wells Nos. 308 and 311 of the Zavardy field of CGTU Mubarek are connected to cathode protection.
Works in this direction are continued by joint efforts of ERIELL Group and Uzbekneftegaz JSC.
Press Service, ERIELL Group